Councillors back the £640m plan for 1,539 homes on the old Thames Valley University site. None are affordable; the legal deal is due by 30 July 2027.

Slough’s Planning Committee has backed plans for 1,539 homes on the former Thames Valley University site in the town centre. None of the homes will be affordable housing.

The developers, Muse and Homes England, announced the decision on Thursday morning. They say they have secured a resolution to grant planning permission from the committee, which met on Wednesday 28 October. They put the value of the scheme, known as the North West Quadrant, at £640 million.

A resolution is not yet a planning permission. The decision notice can only be issued once a legal agreement is signed. The council has not yet published the minutes of the meeting.

What has been approved

The 3.68-hectare site runs between Wellington Street and Stoke Road, next to Slough station. The university left in 2010 and the buildings were cleared in 2020 and 2021. According to the council’s officer report, the scheme includes:

  • 1,214 flats, most of them Build to Rent
  • 325 co-living rooms
  • 25,030 square metres of offices
  • shops, cafes and a gym
  • a children’s nursery
  • a multi-storey car park, with 420 parking spaces across the site
  • buildings of up to about 16 storeys

The first phase has full permission: 501 Build to Rent flats and all 325 co-living rooms, in five buildings of 11 to 15 storeys. The rest has outline permission, so its detailed designs must come back to the council later.

Muse’s announcement describes a “100-child nursery of 450 sqm”. The officer report describes a smaller one, about 86 places in 393 square metres, and that is the size the council asked the developer to build and fit out.

The affordable housing question

Slough’s planning policy asks for 30% to 40% social rented housing on a site this size. The developers’ viability assessment said the scheme would run at a deficit of about £170.5 million. The council’s own consultant, BPS, put it at about £160.8 million, and agreed that no affordable housing could be afforded.

Officers said affordable homes might still come later with government grant from the Social and Affordable Homes Programme. Nothing about that grant is secured. Instead, the legal agreement will include viability reviews at set stages, which could unlock affordable homes if the figures improve.

Muse’s announcement does not mention affordable housing. We covered the full officer report, including the housing mix and why the policy was set aside, in our preview of the meeting.

What happens next

The decision is delegated to the council’s Chief Planning Officer. Permission will be issued once the developers sign a Section 106 agreement. It will cover:

  • education and healthcare contributions, with the amounts still to be agreed
  • £818,496 towards protecting Burnham Beeches
  • transport and highway works, including land for the council’s cycle scheme
  • the nursery, built and fitted out
  • the viability reviews
  • local jobs and training, public art and a car club

The officer report sets a deadline of 30 July 2027 for that agreement. If it is not signed by then, officers recommend refusal unless more time is agreed.

The report expects work to start in 2027 and the whole site to be finished by 2037:

Phase What Start
1 501 Build to Rent flats and 325 co-living rooms 2027, about four years
2 up to 331 Build to Rent flats, the nursery and the car park 2030, about four years
3 an office block and up to 382 Build to Rent and market sale homes 2034, about three years

Hollie Carlile, senior project manager at Muse, called the resolution “an important milestone for the project and for the continued regeneration of Slough town centre”. Charlotte O’Mahony, project director at Homes England, said it would let the partners move forward with “transforming this long-vacant site”.

Muse has worked in Slough for 13 years through its joint venture with the council. Its projects include The Curve, Slough Ice Arena and The Centre.

What it means for you

  • If you are on the housing register, this approval adds no social or affordable homes. Any would depend on a later viability review or a grant that has not been secured.
  • If you rent in the town centre, the first 826 homes will all be Build to Rent flats and co-living rooms, owned by a landlord and let rather than sold.
  • Nothing will be built before 2027. The legal agreement has to be signed first.
  • The meeting papers are on the council’s committee page. The minutes, with the vote, will be added there.