The M25 anti-clockwise shuts through junction 15 every night from Monday 16 to Thursday 19 November. Farnham Road resurfacing nights start on 26 November.
Slough roadworks and travel, checked against the official sources on Friday 13 November 2026. Eight things matter now.
- The M25 anti-clockwise closes through junction 15 every night from Monday 16 to Thursday 19 November, 10pm to 5.30am, between the exit and entry slip roads. That is the M4 interchange for Slough.
- The M25 clockwise closes from junction 13 to junction 14 on Monday 16 and Tuesday 17 November, and from junction 15 to junction 16 on Wednesday 18 and Thursday 19 November.
- The Sheffield Road bus stop at number 6 is suspended from 19 to 21 November. Use the temporary stop outside 33-35 Sheffield Road.
- Kendrick Road in Langley closes from Tuesday 24 to Thursday 26 November, between No. 10 and No. 14.
- Farnham Road resurfacing runs at night from 26 November, starting at the roundabout and moving north to Whitby Road by 5 December.
- No trains run between Maidenhead and Paddington on Saturday 28 and Sunday 29 November, for the Dolphin Junction work. Buses replace them.
- Tuns Lane will close from Cippenham Lane to M4 junction 6 for four days in February, one of five closures the council published this week for January and February 2027.
- The whole A4 through the borough remains a 20mph road until March 2028, and a 20mph limit now covers 35 roads in Colnbrook and Poyle.
The motorway closures this week
National Highways re-issues its seven-day closure report every working day. The edition last updated at 13:15 on Friday 13 November covers 13 to 19 November 2026.
| Night | What closes | Times | Reason given |
|---|---|---|---|
| Fri 13 Nov | M25 clockwise, J14 to J15 carriageway | 11pm to 6am | Retexturing |
| Fri 13 Nov | M25 anti-clockwise, J17 to J16 carriageway | 11pm to 6am | Surfacing |
| Sun 15 Nov | M40 southbound, J2 to J1 carriageway | 10pm to 6am | Emergency routine works |
| Mon 16 to Thu 19 Nov | M25 anti-clockwise, J15 carriageway between the exit and entry slip roads | 10pm to 5.30am | Maintenance |
| Mon 16 and Tue 17 Nov | M25 clockwise, J13 to J14 carriageway | 10pm to 5.30am | Resurfacing |
| Mon 16 Nov | M25 clockwise, J16 link road to the M40 eastbound | 10pm to 5.30am | "Glis removal works" |
| Mon 16 Nov | M4 westbound, J4 entry slip road | 10pm to 5.30am | Horticultural works |
| Tue 17 Nov | M4 westbound, J3 to J4 carriageway, and the J4 eastbound entry slip road | 10pm to 5.30am | Maintenance and horticultural works |
| Wed 18 and Thu 19 Nov | M25 clockwise, J15 to J16 carriageway, slip and link roads | 10pm to 5.30am | Routine maintenance |
| Wed 18 Nov | M25 clockwise, J13 exit slip road | 10pm to 5.30am | Urgent carriageway repairs |
What that means in practice:
- Heading south on the M25 from the M40 towards Heathrow late on Monday to Thursday, the anti-clockwise carriageway through junction 15 is shut between the slip roads. You can still leave at junction 15 for the M4 and Slough. National Highways signs a diversion on its own roads.
- Heading north from junction 15 towards the M40 on Wednesday and Thursday nights, the clockwise carriageway is shut from junction 15 to junction 16, slip and link roads included.
- Driving north on the M25 from Staines towards Heathrow on Monday and Tuesday nights, the clockwise carriageway is closed from junction 13 to junction 14.
- On the M4 at the London end, the westbound carriageway closes from junction 3 at Hayes to junction 4 at Heathrow on Tuesday night.
- Nothing is booked on the M4 at junctions 4B to 7 in this edition. The roundabout at junction 8/9 near Maidenhead has partial overnight closures for surveys on most nights.
The report runs a week ahead only. It books no M4 closures at junction 4B, but the six-month order means more nights there are likely; our story explains the hours it allows.
Trains: a Sunday, a November weekend and Christmas
National Rail’s engineering notices through Slough now run to January. The biggest are the two Dolphin Junction closures, set out below. We rechecked the 15 and 28 November notices on 13 November; the later ones are as National Rail published them when we checked on 16 October.
Sunday 15 November: buses between West Drayton and Slough before 8am. A shuttle train runs between Slough and Reading, the 06:20 from Reading terminates at Slough and the 06:38 from Paddington starts there, and after 10am the Elizabeth line again terminates at Paddington, with two trains an hour at Maidenhead, Burnham, Slough, Langley and West Drayton.
Saturday 28 and Sunday 29 November: no trains between Maidenhead and Paddington. Work at Dolphin Junction, near Slough, closes all lines. The only Elizabeth line trains are two an hour between Reading and Maidenhead. Buses run between Maidenhead and Slough, and between Slough and Ealing Broadway. There are no Elizabeth line or Heathrow Express trains to Heathrow all weekend.
Saturday 5 and Sunday 6 December: two of the four lines close between Hayes & Harlington and Slough. Before 8am on the Sunday no trains run between West Drayton and Slough, with buses from Hayes & Harlington instead.
Sunday 27 December to Sunday 3 January: no trains between Slough and Paddington. From 27 to 30 December the Elizabeth line does not run west of Paddington and Great Western runs only between Slough and Reading, with buses from Slough to Ealing Broadway. From New Year’s Eve the Elizabeth line runs as far as Hayes & Harlington, with buses on to Slough. National Rail’s Dolphin Junction page has the plan, and our story sets it out day by day.
The A4 is a 20mph road, and the order runs to 2028
This is still the biggest change on Slough’s roads, and it was made with a statutory notice rather than an announcement.
Slough Borough Council’s Order 18 of 2026 varies the speed limit on the A4 Bath Road, High Street and Wellington Street from 30mph to 20mph in both directions. It runs from the borough’s western boundary, about 40 metres west of the Huntercombe Lane North and Huntercombe Lane South junction, to a point 215 metres east of Wexham Road. That is effectively the A4 across the whole borough.
The order does four things:
- drops the limit to 20mph on the A4 and on Farnham Road, from the A4 to Whitby Road
- allows road closures on the same two stretches
- bans pedestrians and cyclists from the footway inside the works area
- allows a contraflow on the A4, running westbound traffic on the eastbound carriageway and the reverse, under controlled traffic management
It came into operation at 00:00 on Monday 14 September 2026 and lasts 18 months. The works are expected to be finished by 23:59 on Tuesday 14 March 2028. The sealed order, listed as the A4 Cycle Lane Order on the council’s temporary orders page, is dated Made: 21 September 2026, a week after it came into operation, and its terms match the notice.
This is a temporary works order, not a new permanent limit. It exists to let the A4 cycle lane be built, and on its own terms it expires when the works finish.
What is coming: Kendrick Road, Tuns Lane and Deal Avenue
| Road | Extent | Dates | Order |
|---|---|---|---|
| Deal Avenue | Dover Road to Henley Road | 19 October to 11 December, start not confirmed | Order 31 of 2026, made 18 September |
| Kendrick Road, Langley | No. 10 to No. 14 | 24 to 26 November | Order 33 of 2026, made 23 October |
| Market Lane, Langley | 1 Market Lane to Grand Union Place Mobile Home Park | 17 and 18 January 2027 | Proposed |
| Faraday Road | Furnival Avenue to Franklin Avenue | 18 to 21 January 2027 | Proposed |
| Beaumont Road | St Elmo Crescent to Villiers Road | 3 and 4 February 2027 | Order 37 of 2026, made |
| Tuns Lane | Cippenham Lane to M4 junction 6 | 8 to 11 February 2027 | Order 32 of 2026, made |
Deal Avenue is the one to note, and the one we cannot confirm. The order was due to come into operation at 00:01 on Monday 19 October, with works expected to be complete by 23:59 on Friday 11 December 2026. That is close to eight weeks with no traffic passing between Dover Road and Henley Road. The council said an alternative highway would be available and diversions signed on site. The notice was published on 18 September through the Public Notice Portal, where it was still listed when we checked on 22 September. It has since rolled off the portal’s current Slough listing, and it has never appeared on the council’s own orders pages or its temporary orders list. It was still missing from that list on 13 November. Nothing has been published to withdraw it, and nothing to say the closure has started, so allow for Deal Avenue being shut until the council says otherwise.
Kendrick Road in Langley closes for three days from Tuesday 24 November. The council made the order, Order 33 of 2026, on 23 October, a week after its proposed order. It stops traffic between No. 10 and No. 14 Kendrick Road, SL3, from 00:01 on 24 November, with the works expected to be complete by 23:59 on Thursday 26 November. Queries go to street.works@slough.gov.uk or 01753 475111. Access is kept for residents and businesses, with a local diversion signed. The notice does not say what the works are. It is separate from the speed cushions proposed for Horton Road, which are a permanent scheme.
Tuns Lane will close for four days in February, between Cippenham Lane and M4 junction 6. Tuns Lane is the A355 link from the town to the motorway. The council published a notice of intent dated 6 November, and then a made order, Order 32 of 2026, dated 13 November. It comes into operation at 00:01 on Monday 8 February 2027, with the works expected to be complete by 23:59 on Thursday 11 February. Neither notice says what the works are. Local diversions will be signed, and access is kept for residents and businesses.
Four more closures are booked for January and February. All were published on 13 November, and none says what the works are:
- Market Lane, Langley, from 1 Market Lane to Grand Union Place Mobile Home Park, on 17 and 18 January 2027. This is a proposed order.
- Faraday Road, from Furnival Avenue to Franklin Avenue, from 18 to 21 January 2027. Also proposed.
- Beaumont Road, from St Elmo Crescent to Villiers Road, on 3 and 4 February 2027. This one is made, as Order 37 of 2026. The council used the same number for the Station Road closure in Langley in October.
Queries on all of them go to street.works@slough.gov.uk or 01753 475111.
Six roads are down for resurfacing closures of up to ten days each, with no dates yet. The council’s notice for additional road closures, dated 12 June, covers Wellington Street (Uxbridge Road roundabout to Langley Road), Oatlands Drive (Birley Road to Loddon Spur), Lower Britwell Road (Haymill Road to Farnham Lane), Bower Way (Elmshott Lane to Hinton Road), Blackthorne Road (Horton Road to David Road) and Stoke Poges Lane (Northern Road to Regent Court). It runs from 13 July 2026, with the work expected to be finished by 31 March 2027. The closures will not run at the same time, some will be overnight, and access is kept for residents and businesses. The council says advance warning signs on each road will give the dates; it has not published them.
Holmlea Walk in Datchet closes for a day on Monday 16 November. The Royal Borough published the order on 30 October and again on 13 November, with the same date. It shuts Holmlea Walk from the B376 Horton Road to Talbot Place from 8am to 5pm, for carriageway repairs. The notice says there is no alternative route.
Colnbrook and Poyle now have a 20mph limit on 35 roads. The council made the order, Order 19 of 2026, on 8 October, and it came into force on 19 October. The notice was published on 23 October. It covers High Street Colnbrook, Bridge Street, Park Street, part of London Road and part of the Bath Road, plus the residential streets around them. Separately, the council plans two sets of speed cushions and a speed table on Horton Road; comments closed on 16 October. We have written up both schemes in full.
Dennis Way and Plackett Way in Cippenham would become a School Street. The council published Order 20 of 2026 on its permanent orders page on 25 September. Both roads would close to traffic from 8am to 9am and 3pm to 4pm on weekdays, except for cyclists, permit holders and emergency vehicles. Objections closed on 16 October, and by 19 October the council had published no decision. The notice’s permit clause names Moat Drive, a street in Wexham, rather than Plackett Way. We have set out the detail.
Two crossings on National Cycle Network route 461 would become toucan crossings. The council published the proposal on 6 November. The existing signal crossings on Cumberland Avenue and Sheffield Road, where the cycle route crosses them, would be converted so cyclists can use them too. The Cumberland Avenue crossing would be widened from 3.6 metres to 4.8 metres.
The council also plans a raised zebra crossing on Essex Avenue, where the same route crosses near Sheffield Avenue. Its notice gives the table as 8.75 metres long and 75mm high, across the full 6.2-metre width of the road. Comments on both go to TransportPlanning@slough.gov.uk by 27 November. The plans can be seen at Observatory House and The Curve.
The bus station access road gets no waiting or loading at any time from 20 November. The council’s notice of 6 November said the experimental order, Order 22 of 2026, came into force on 13 October. A fresh notice published on 13 November says the council made the order on 12 November and that it comes into force on 20 November. The two notices do not agree, and the later one does not explain the change. Objections can be made for six months from the day it came into force, to parking.consultations@slough.gov.uk.
The short-stay bays on High Street, Langley, at Willoughby Road, change on 20 November. Under an experimental order, Order 23 of 2026, made on 12 November:
- the bays will apply at all times, with a 30-minute maximum stay and no return within two hours (at present it is 20 minutes, from 1pm to 10.30am)
- they will be 14 metres longer
- the zig-zag lines at the crossing outside No. 252 High Street will be shortened to make room
Just over the border in Buckinghamshire, the county has made an order closing about 53 metres of Britwell Road, Burnham, for coring works from 29 October. It is in the county’s statutory notices on the Public Notice Portal, which give no end date beyond the order’s 18-month maximum. The alternative route is Hogfair Lane and Lower Britwell Road.
What is being built on the A4, and how long it is meant to take
The order above exists because of the A4 cycle lane. The council secured £10.4 million from the Department for Transport and Active Travel England for a two-way cycle lane, about 2.5 metres wide and mostly segregated, running alongside the A4 Bath Road from the Huntercombe Lane crossroads to Uxbridge Road. It is being built in three phases: Huntercombe Lane North to Dover Road, Dover Road to Pitts Road, then Pitts Road to Uxbridge Road via the High Street and Wellington Street.
The council publishes a provisional timeline for the major highway works, section by section. It runs to May 2028, and it is the single most useful document on the scheme if you drive or cycle the A4.
The provisional dates, as the council publishes them:
- Huntercombe Lane crossroads to Goldsworthy Way: 12 January to 31 March 2026
- St Andrews Way to Elmshott Lane and Station Road: July to November 2026
- Elmshott Lane to Burnham Lane: November 2026 to May 2027
- Tuns Lane to Montem Lane: November 2026 to May 2027
- Burnham Lane to Dover Road: April to July 2027
- Dover Road to the Pitts Road crossing: June 2027 to April 2028
- Montem Lane to Stoke Poges Lane: May 2027 to March 2028
- Stoke Poges Lane to Wexham Road: March to May 2028
The council warns that the programme may change and that traffic management plans are subject to change at short notice.
Its A4 works diary has not moved since 7 September, which is 56 days. Three things from that entry are still on the record, and one of them has fallen due:
- Ducting for new traffic signals continues at the St Andrew’s Way junction with Bath Road. Works at that junction are expected to run until early December, and include new crossing points, new signals, revised islands and the closure of the service road that comes out into St Andrew’s Way.
- A 28-day concrete curing period is running on the service road by the Mini garage. Resurfacing follows once it is complete.
- The new entry into that service road, coming off the Huntercombe roundabout, is expected to be open by 28 September. That date has passed, and the council has published nothing to say whether it opened.
Farnham Road: resurfacing nights and two bus stops
Destination Farnham Road is rebuilding the A355 from the Bath Road junction north through the shopping stretch. It started on 17 November 2025 and it is still the main source of delay in the borough. Farnham Road from the A4 to Whitby Road also sits inside the A4 order, so that stretch is 20mph too.
Two dates from the council’s own updates are the ones to plan around.
- The Three Tuns junction is on temporary lights for six months. The update of 15 July 2026 records that the switch was made at the weekend of 11 and 12 July, which runs the six months to roughly mid-January 2027.
- The Bath Road to Farnham Road section was due to run to approximately mid-October. It is now November, and the council has neither updated that estimate nor said the section is finished. Work on that stretch started on 22 July 2026 and covers realignment of the central island, drainage, ducting, footway and carriageway works.
The council also confirms that the dedicated left-turn lane from Bath Road, outside the Tuns pub, into Farnham Road is closed and will not be reinstated once works are complete.
The council’s latest update is dated 12 November. The Destination Farnham Road updates page says resurfacing will run at night, 9pm to 5am:
| Where | Nights |
|---|---|
| Farnham Road roundabout | 26 to 27 November |
| Farnham Road at the Sheffield Road junction | 1 to 3 December |
| Buckingham Avenue to Whitby Road | 3 to 5 December |
The council says most of the noisy work will be done before midnight, with quieter work through the night. Warning and diversion signs will be up, and access is kept for residents.
Two bus stops are affected:
- 6 Sheffield Road is suspended from 19 to 21 November, for footway and cycle lane work. Use the temporary stop outside 33-35 Sheffield Road.
- The southbound stop opposite Lidl on Farnham Road stays suspended until 10 December. The temporary stop is opposite the Lebanese Grill, at 316-320 Farnham Road.
Neither update says anything about the Bath Road section’s mid-October estimate.
The £9.3 million for the scheme came from the Department for Levelling Up, Housing and Communities in February 2023. It is not resurfacing: the finished road is meant to carry a 20mph limit through the shopping area, two-way cycle routes, rebuilt crossings, upgraded lighting, better bus stops, revised parking, park improvements and sustainable drainage.
Five other major highways schemes are live or in preparation alongside it: the Poyle Road bus gate, Stoke Road area regeneration highway works, High Street Langley widening and junction signalisation, Slough Mass Rapid Transit Phase 2, and the Colnbrook and Poyle 20mph and Horton Road traffic calming proposals.
What has finished, and what we could not confirm
Station Road in Langley was due to reopen at 23:59 on Sunday 1 November, after a week closed between Waterside Drive and Alderbury Road under Order 37 of 2026. The council has published nothing to say the works overran.
Banbury Avenue’s back-up dates ended on 1 November. The crane closure on the Slough Trading Estate, from Dundee Road to number 8, under Order 42 of 2025, had primary dates of 7 September to 5 October and back-up dates to 1 November. Neither the council nor the contractor ever said which dates were used.
Horton Road in Colnbrook was due to be shut from 28 to 30 October, between Popes Close and the High Street, under Order 21 of 2026. The council’s temporary orders list carries a “Colnbrook and Horton Road TTRO”, but nothing says whether the closure went ahead. Either way, the dates have passed.
Keate’s Lane in Eton, closed nightly with a diversion through Slough, was booked until Monday 2 November under the Royal Borough’s order, so the last night has passed.
Albert Street, from Windsor Road to Upton Park, was proposed for closure over the weekend of 26 and 27 September. The council only ever published a notice of intent for it, dated 31 July, and no sealed order has appeared since, so we cannot say whether the closure went ahead. Either way, those dates have passed.
The Royal Windsor Way nights have passed. The A332 was booked to close from 9pm to 6am, Monday 9 to Thursday 12 November, for signal works at M4 junction 6. The National Highways report for 13 to 19 November books no follow-on nights at junction 6.
Remembrance Sunday’s road closures were for 8 November only, in the town centre, Langley and Cippenham.
Earlier motorway closures have finished. The M25 clockwise junction 14 to junction 15 nights ran from 9 to 11 November, with one more booked for Friday 13 November. The M25 anti-clockwise junction 16 to junction 15 nights, and the M4 eastbound junction 3 to junction 1 nights, have passed.
The October and early November rail work is over. That includes all the Burnham late-train closures, the last on 7 and 8 November, and the Sunday 1 November line closure between Paddington and Southall.
Waterside Drive is not closing. A notice on the Public Notice Portal dated 16 October is headed “Waterside Drive, Slough - Road Closure”, but its text is a planning application, P/01053/027, to demolish and rebuild at Langley Quay Business Park. It closes no road.
Albion Close was booked for a single night, from 23:30 on 3 October to 06:00 on 4 October, for work on the telecoms mast at the Petersfield Avenue junction.
The telecoms work on Bath Road for euNetworks, which banned the right turn into Ledgers Road, was scheduled by JSM Group Services for 19 and 20 September and those dates have passed. The sealed order behind it, the Slough Borough Council (Bath Road) Order 2026, Order 6 of 2026, still runs to late 2027, so further lane closures can be taken under it without a fresh order. The council has published nothing to say the work is complete.
The order covering 1.2 kilometres of National Cycle Network route 461, from the borough boundary next to 93 Wiltshire Avenue in SL2 to a point 40 metres south of the Belfast Avenue junction in SL1, said the works were expected to be complete by 23:59 on Sunday 13 September 2026. Eight weeks on, the council has published nothing to confirm that they were. The order itself was made for six months from 20 July, so it can still stand. Note that it closes the cycleway, not Belfast Avenue.
The parking rules that changed in August, and are still in force
Three orders made by Slough Borough Council came into force on 21 August 2026, all published as statutory notices signed by Matthew Hooper, the council’s Director of Environment and Highways. They are settled now, but they are recent enough that plenty of drivers have not caught up with them.
Waiting and loading restrictions changed on 25 roads. Amendment No. 57 altered waiting and loading restrictions and parking places on parts of these roads, and updated existing orders covering controlled parking zones B and E:
- Albert Close, Albert Street, Alpha Street South
- the Bath Road service road in front of numbers 135 to 147
- Bishops Road, Castle Street, Charter Close, Church Street, Clifton Road
- Glentworth Place, Grove Close, Hanover Close
- Hencroft Street North, Hencroft Street South, Herschel Street
- the High Street Chalvey service road in front of numbers 15 to 31
- Mere Road, Merton Road, Osborne Street, Park Street
- St Laurence Way, Sussex Place, The Grove, Upton Park, Victoria Street
One caution. The notice was headed “(PROPOSED ORDER)”, but its own text said the council made the order on 20 August and that it came into force on 21 August. Check the plans on the council’s orders page before you assume the lines outside your door have changed.
Elmhurst Road in Langley now has resident permit parking, plus waiting and loading restrictions at all times next to number 1a. Permits are available to the odd numbers 1a, 1 to 33, 33a and 35 to 47 on the north side, and the even numbers 2a and 2 to 48 on the south side.
A 40mph order covers seven roads, but nothing changed on the ground. The council consolidated its historic 40mph limits into one order covering Wexham Road, Uxbridge Road (A412), Sutton Lane, Hurricane Way, Hollow Hill Lane, Slough Road (A332) and Ditton Park Road. Its own statement of reasons calls it an update and consolidation of historic orders.
The routes that carry Slough
The borough is 32 square kilometres and almost every journey uses one of five things.
- The A4 Bath Road runs the length of the borough east to west, through the town centre and past the trading estate. It is the road that fails first when the M4 closes, and it is now 20mph along its whole length here.
- The A355 Farnham Road is the main north-south route, up towards Farnham Royal and Beaconsfield. It is the one being rebuilt.
- The M4 runs along the south. Junction 5 serves Langley, junction 6 the town centre, junction 7 the west of the borough, and junction 4B is the M25 interchange to the east.
- The A412 runs south through Langley to Datchet and north to Uxbridge.
- The M25 is minutes away to the east at Colnbrook and Poyle, which is why a problem at M25 junction 14 or 15 becomes a Slough problem within the hour.
Where we check, and where you can check
- Slough Borough Council’s temporary traffic orders and permanent orders, which carry the sealed orders, the notices of intent and the contractors’ letters.
- The National Highways seven-day closure report for the M4 and M25, republished twice daily on working days.
- The council’s A4 cycle lane and Destination Farnham Road project pages.
- The Public Notice Portal, which sometimes carries a Slough order before the council’s own pages do.