Microsoft says it will apply this autumn to build a data centre by Langley station, with building work from 2027. What the plans show, and how to comment.

Microsoft plans to submit a planning application this autumn for a data centre on the former Langley Business Centre site, next to Langley station. It hopes to start building in 2027.

The timetable comes from the consultation boards Microsoft showed residents at Langley College on 14 and 15 July. The company held a second drop-in at Langley Community Centre on Saturday 12 September, according to its Langley project page.

Microsoft calls the dates “tentative”. It says they “may change, and are reliant on the planning process”.

What Microsoft is proposing

The boards describe one data centre building, with data halls, offices and support facilities. Microsoft says its height “will be similar to that of a six storey office building”.

The plans include:

  • a substation, which Microsoft says will need a separate planning application
  • secure car and cycle parking, with electric vehicle charging
  • a loading bay and ramp, and sustainable drainage
  • acoustic screening around the site “to mitigate any noise generated”
  • a public footpath through a wildflower meadow between Station Road and Mead Avenue
  • public art commissioned locally
  • keeping the mature boundary trees that screen neighbouring homes

The drawings of the views from homes to the south and east show chimneys. Microsoft says there “will be additional screening around the chimneys” and that the design may still change.

What has to be assessed

Microsoft says an Environmental Impact Assessment is under way. It will cover air quality, noise, climate, townscape, and daylight and sunlight. Noise modelling is looking at both the data centre and the substation.

The council’s planning register shows the formal first step. A request for an environmental scoping opinion, reference P/00437/096, was received on 14 May 2026. A scoping opinion sets out what the assessment must cover. The council’s planning portal still lists the request as undecided, and its documents were not on the council’s document search when we checked today.

On traffic, Microsoft says early indications are that the data centre would generate less traffic than the scheme approved in 2021, and less than the old business park did. A full Transport Assessment will come with the application.

A bigger plan in 2024

An earlier scoping request for the same land was made in March 2024. Its scoping report, reference P/00437/095, was written by the consultants Ramboll for MSFT MCIO Ltd. It described a larger scheme:

  • an 83,960 square metre data centre campus
  • two data centre buildings joined by an administration block
  • buildings of about 21 metres, rising to 26 metres in the centre
  • back-up diesel generators for use if the National Grid fails

The 2026 boards describe a single building. They do not give a floor area or a generator type. Microsoft’s global targets on the boards include “eliminating the use of diesel for backup power by 2030”.

Is the old permission still alive?

Microsoft’s own documents give two different answers.

The council granted outline permission, P/00437/093, on 29 January 2021. The Planning Committee record describes a data centre of up to 93,000 square metres on one plot and up to 60 homes on the other.

The 2024 Ramboll report said all pre-commencement conditions had been discharged and demolition carried out, so the permission “has therefore been implemented and is extant”. The 2026 consultation boards say the 2021 application “has now lapsed”, and that the new plans differ from it.

That matters. A live permission is a fallback a landowner can build out if a new application fails. The planning application should make clear which position Microsoft is taking.

Langley Business Centre site: from outline permission to a Microsoft data centre A timeline. 29 January 2021: outline permission P/00437/093 for a data centre and up to 60 homes. December 2023: site vacant and largely cleared. 28 March 2024: scoping request P/00437/095, prepared for MSFT MCIO Ltd, for an 83,960 square metre, two-building campus. 14 May 2026: new scoping request P/00437/096. 14 and 15 July and 12 September 2026: public drop-in sessions. Autumn 2026: planning application due. Late 2026: planning process concludes. 2027: construction start. The last three dates are Microsoft's tentative timetable. Langley Business Centre: the road to a Microsoft data centre Council planning records, and Microsoft's own tentative timetable (hollow markers) 29 Jan 2021 Outline permission P/00437/093: data centre plus up to 60 homes Dec 2023 Site vacant and largely cleared 28 Mar 2024 Scoping request P/00437/095: 83,960 sq m, two data centre buildings 14 May 2026 New scoping request P/00437/096, still undecided Jul, Sep 2026 Drop-ins: Langley College 14 to 15 July, Community Centre 12 Sept Autumn 2026 Planning application due to be submitted Late 2026 Planning process concludes 2027 Construction start Sources: Slough Borough Council planning register and committee record; Ramboll scoping report, March 2024; Microsoft consultation boards, July 2026. Graphic by Slough Daily
The last three dates are Microsoft's own, and it says they may change.

The petition

A council ePetition asking Slough to pause approvals of new data centres names “Microsoft’s proposed data centre next to Langley Train Station”. It had 619 signatures today on the council’s petitions list, up from 285 when we first reported it on 21 August. It closes on 16 November 2026.

That is likely to be around the time Microsoft’s application lands. A petition cannot stop an application being made or decided, but its concerns can be raised as objections once the application is open for comment.

What it means for you

Nothing can be formally objected to yet, because no planning application has been submitted. What you can do now:

  • Send Microsoft your views. Download its feedback form and email it to UKDC@microsoft.com. Microsoft’s community team is also on 0800 915 3677.
  • Watch for the application. When it is registered it will get a reference number and a period for public comments. We will list it on Slough planning news.
  • Comment to the council, not only to Microsoft. Comments to the developer are not objections. Only comments made on the application itself go to the council’s planning officers.

If you live near Station Road or Mead Avenue, the chimneys, the noise screening and the new footpath are the details to look for in the drawings.

Sources