The petition to pause new data centres in Slough has 1,517 signatures, past the 1,500 that forces a full council debate. It closes on Monday 16 November.

A petition asking Slough Borough Council to pause new data centres has passed 1,500 signatures. Under the council’s rules, that is enough to force a debate at a full council meeting.

The count on the council’s ePetition page stood at 1,517 on Thursday 12 November. It was 1,248 eight days earlier. The petition closes on Monday 16 November.

The petition asks the council “to pause the approval of new data centre developments until an independent assessment has been carried out into their cumulative impact on residents, infrastructure and the environment”. It names Microsoft’s planned data centre next to Langley station.

What 1,500 signatures means

The council’s petitions scheme says a petition with 1,500 valid signatures “will be debated at a full Council meeting”. The council checks signatures before it counts them, so the final valid total may differ from the figure on screen.

If the petition qualifies, the scheme sets out what happens:

  • the council “will endeavour” to hold the debate at its next meeting, or the one after if that is not possible
  • an officer report sets out the subject and what the council is being asked to do
  • the organiser, or someone they nominate, can speak for up to five minutes
  • councillors debate it for up to 15 minutes, which the Mayor can extend
  • the meeting should decide what to do next, since the scheme says it “will not normally be sufficient” just to note the petition
  • the organiser is normally told the decision within five working days

The next full council meetings are on Thursday 26 November 2026 and Thursday 28 January 2027, according to the council’s meetings calendar. The council has not yet said which meeting will take it.

How fast it grew

The petition opened on 17 August. It had 285 signatures in its first four days and passed 750 in the autumn. That lower threshold calls a lead councillor or senior officer to give evidence at the Overview and Scrutiny Committee.

Line chart of signatures on the Slough data centre petition: 285 on 21 August, 506 on 4 September, 542 on 8 September, 619 on 16 September, 1,248 on 4 November and 1,517 on 12 November 2026.
Signatures as shown on the council's ePetition page on the dates we checked. The dates are not evenly spaced. Chart by Slough Daily
Share this chartFacebookWhatsAppX

What a debate can and cannot do

A debate does not stop any planning decision on its own. The Slough Trading Estate is covered by a Simplified Planning Zone, adopted on 12 November 2024 and running to 11 November 2034. It allows data centres there without individual planning applications. The largest recent scheme, at Manor Farm, was approved by a government minister in June. Our earlier report on the petition sets out both in detail.

Where a decision belongs to the Cabinet, the scheme says full council decides whether to make recommendations to it.

What it means for you

  • You can still sign until Monday 16 November. Signing needs a free account on the council’s democracy website.
  • You can watch the debate. Full council meetings are held in public at Observatory House and the papers are published about a week before.
  • Two more schemes are in the pipeline. The Manor Farm West application at Poyle is still undecided, and Microsoft has said it will apply this autumn for a data centre by Langley station.