The council's own readiness check says its Local Plan team is two officers and the December 2028 target is at significant risk. Comments reopen on 18 January.
Slough Borough Council says there is a significant risk that its new Local Plan will not be ready on time. The plan will decide where homes, jobs and green space go in the borough up to 2046.
The warning is in the council’s own Gateway 1 self-assessment summary, published on 30 October. Every council starting a plan under the new national system has to publish one. It is a check on whether the council is ready to begin a fixed 30-month process that ends with an adopted plan.
The council’s answer is a qualified yes. Its Gateway 1 page says the 30-month period “is achievable”, but that “there are substantial risks in being able to deliver the plan in this time period”.
What the council says is holding it back
The summary is unusually frank. It says:
- the Local Plan Task Force “currently comprises two officers”
- “a number of posts remain vacant, and specialist capability has not yet been secured”
- a vision for the plan and measurable outcomes “have not yet been developed”
- the overall scope of the plan “is not yet confirmed”
- the Authority Monitoring Report, which tracks how the current plan is working, “needs updating”
The council’s readiness checker dates the two-officer figure to 12 October. It adds that recruitment “is expected to commence shortly”.
The summary also names the outside risks. They are staffing, “timely governance decisions”, the evidence the plan needs, national planning reforms, the new Thames Valley Spatial Development Strategy and Heathrow.
It concludes: “Unless these risks are addressed quickly, there is a significant risk that the Council will not prepare and adopt the plan within 30 months.”
Why Heathrow matters so much
The council calls Heathrow “a particularly important dependency”. Two separate expansion proposals are being worked up alongside the Local Plan. The summary says they “could affect its assumptions about land use, transport, infrastructure and the environment”.
Its answer is to plan for more than one outcome. The council says it “will use scenario planning and regularly review our assumptions as the Heathrow proposals develop”. Heathrow’s own consultation on its third runway plans runs until 22 December.
A gap in the summer consultation
The first stage of the plan was a scoping consultation, which ran over the summer. The summary says “a recent omission from the consultation process identified missing consultees and weaknesses in notification and audit assurance”.
The council is now running what it calls “corrective consultation and associated compliance checks”. Until those are finished, the readiness checker says, “it cannot be confirmed that all legal requirements have been fully met”. It does not say which consultees were missed.
The council also accepts that people “need clearer and more useful online maps”. It is working on a business case to buy a new digital mapping system by February 2027.
The timetable
The published timetable was last updated on 30 October. The dates have not moved.
| Stage | Date |
|---|---|
| Consultation on proposed plan content and evidence | 18 January to 1 March 2027 |
| Gateway 2 review by an assessor | 24 May 2027 |
| Consultation on the proposed Local Plan | 11 October to 6 December 2027 |
| Gateway 3 review | 2 June 2028 |
| Submission to the Secretary of State for examination | 21 June 2028 |
| Adoption | 20 December 2028 |
The council says it will review the timetable and update it at least monthly if dates change.
Slough is still deciding planning applications against a Core Strategy written for 2006 to 2026. The new plan will replace it.
What it means for you
The next chance to comment is the consultation on proposed plan content and evidence, from 18 January to 1 March 2027. The timetable says the council does not intend to hold any other consultations beyond the ones the law requires. That makes the January stage, and the one in October 2027, the two points where residents can shape the plan.
To be told when consultations open, the council asks people to email planningpolicy@slough.gov.uk and ask to join its consultation database. The new Local Plan pages carry the documents.
The council says it expects to appoint specialists for the plan’s environmental assessment during November.
Have your say